The project started out normally with velocity starting to converge around the third and fourth iteration. By the fifth or sixth iteration ve-locity started to drop off. The project was in serious trouble by the ninth iteration. The next step is figuring out why.
|
||
|
|
||
|
7.6 What Goes Wrong?
Finding the root cause for a velocity trend change can be difficult. In this project, we had a problem with quality which was indicated by an increase in the number of stories to fix defects. This was obvious when reviewing the story cards. When I went back to review the cards for this chapter, it struck me that the task estimates seem shorter as the project progressed. While I don’t recommend tracking average task length in general, the graph illuminates the problem in this case:
Troubled Project’s Average Task Length Graph
Copyright © 2004 Robert Nagler 51